Dash Point's Pier Now Waits on Permits and a Salmon Calendar

The Dash Point Pier at 1500 Beach Dr. NE has been closed to the public since July 2021. The closure covers more than the deck. Parks Tacoma says going on or under the pier, on foot or by boat, is unsafe and prohibited. The rest of the beach at Dash Point Park stays open, while the pier itself sits off-limits.

In late April 2026, 77% of Park District voters approved a $155 million bond package, and "Redevelopment of Dash Point Pier" is on its project list. That vote resolved the funding question. The pier's timeline now depends on a set of environmental permits and on the few months each year when in-water work is allowed in Commencement Bay.

The Vote Settled the Money Question

As recently as September 2025, money was the whole problem. That month Parks Tacoma announced the pier's design progress and said there was "currently no funding to renovate the pier or make park improvements," estimating that finishing the project would cost "upwards of $5.5 million." Planning and design had already used $715,000 from a 2014 voter-approved bond and an aquatic lands enhancement grant from the Washington State Recreation & Conservation Office.

The April 2026 bond moved the pier from "no funding" onto a funded list. The bond page describes more than 100 projects across the city, "designed to be implemented over a six-year period." It does not show a dollar amount for Dash Point or say which of the six years the pier falls in. The $5.5 million figure is a 2025 estimate made before the bond passed, and it should be read as that and nothing more.

Seven Years Into a Twenty-Year Forecast

The pier's history explains why a full rebuild is on the table and a repair is not.

Year What happened at Dash Point
1917 Public fishing from a pier at this site begins
1923 Dash Point Park annexed to Parks Tacoma
1949 Dash Point Dock deeded to Parks Tacoma
1995 Concrete pier nearly 500 feet long built with a $929,721 state grant
2014 Engineering review estimates 20 to 30 years of remaining life
July 2021 Pier closed after a structural assessment
Oct 2023 Redesign process begins
Oct 2025 Project marked "Ready for Environmental Permitting"
April 2026 Bond including pier redevelopment approved

The 2014 review gave the concrete pier 20 to 30 more years. It closed seven years after that review, following a preliminary assessment completed July 23, 2021. Based on its engineering analysis, Parks Tacoma now says the work will mean "full reconstruction/replacement of the pier."

What Is Actually Being Permitted

Under the current design, the replacement pier keeps its length and is built with new steel piles, concrete pile caps, a grated platform, and steel rails. It may add bumpouts so people can pass one another, along with fish-cleaning stations. The deck would sit about three feet higher than today's to allow for sea-level rise projections and stronger storms. That is a design concept, and the details can still change.

The rest of the park is part of the plan too. At an October 6, 2025 meeting at the Center at Norpoint, Parks Tacoma staff and consultant MacKay Sposito presented a design development plan for the pier and a schematic design for the whole park. Topics included a picnic shelter, playground equipment, the basketball and tennis court, walkways, plantings, parking, beach use, and sea-level change.

Kristi Evans, the capital program manager, described the place in the 2025 announcement:

"Dash Point Park is a special place both for anglers who want to cast a line into the shoreline waters but also those who simply want to take in the beauty of Commencement Bay and Tacoma's shoreline."

The Paperwork the Bond Doesn't Skip

The October 2025 presentation includes a slide of future steps. Even with funding secured, the project still has to work through:

  1. A Joint Aquatic Resources Permit Application
  2. A Hydraulic Project Approval from the Washington Department of Fish and Wildlife
  3. A Shoreline Substantial Development Permit
  4. A Pierce County building permit
  5. Construction and bid drawings
  6. Securing funding
  7. Construction

The bond passed, so the funding step has moved forward. The four permits ahead of it haven't moved publicly. The latest entry on Parks Tacoma's project page is still headed "October 2025." On October 22, 2026, NE Tacoma Buzz rechecked the page and reported that it lists no construction start date or reopening date.

Some of these steps are fairly quick on their own. WDFW says it typically has 45 days to decide a complete HPA application. But the order matters. Bid drawings follow the permits, and construction follows the bids.

A Salmon Calendar Sets the Construction Season

Every permit on that list feeds into one constraint, which is when crews can work in the water. Under the state's hydraulic code, Tacoma waters north of the Narrows Bridge fall in Tidal Reference Area 4. The rule sets "July 15 - February 15 for all work in Commencement Bay" to protect juvenile salmon while they migrate, feed, and rear. WDFW says the authorized work times for any project are written into its own HPA, so the Dash Point permit will set the actual dates.

Driving steel piles into the bay bed is in-water work. Under the general rule, that leaves roughly seven months a year when the job can happen, from mid-July to mid-February. From mid-February to mid-July, crews generally stay out of the water. Any construction plan for the pier has to fit inside the dates its HPA authorizes.

The site's history shows how much this work involves. Engineering consultants finished in-water and upland core sampling in November and December 2024, then did more geotechnical exploration for seismic analysis. That groundwork is done. Building on it requires the permits.

Capital Money Can't Fix an Operating Squeeze

Parks Tacoma has a second calendar running alongside the pier, and it's easy to confuse with the bond. As the agency closed its 2025 books, actual revenue came in $4 million below the revised General Fund budget, which meant cutting about $9 million before the end of 2026. Parks Tacoma says some programs have already been scaled back. Its budget page also states that bond funding "is highly restricted under state law and cannot be used for the operating budget."

The Board of Park Commissioners held the first reading of the 2027 budget on October 26, with a second reading and vote set for November 9. The October 26 agenda covered the budget, the levy, and bond redemption. It didn't list any item on the Dash Point Pier.

These are two separate processes. The pier's construction money is protected from the operating cuts, and the operating cuts can't draw on that money. The vote that funded a new pier says nothing about the hours, programs, and maintenance staffing that operating dollars pay for across the district.

This Winter at the Water's Edge

Until the pier reopens, the shoreline around it is still usable, and several things on the calendar are worth knowing:

  • Dash Point Park beach. Only the deck and the area under the pier are closed. Parks Tacoma's restroom schedule lists the Dash Point Park & Pier restroom building as open from October 1, 2026 through April 30, 2027.
  • Fishing elsewhere. Dash Point Park has no other designated fishing area. Parks Tacoma suggests Les Davis Pier and the Point Defiance Marina, and points to WDFW's list of fishing piers.
  • Dash Point State Park. Day use stays open through winter. The upper campground loop closes September 15 to May 15, and severe weather can cause other closures, according to the State Parks winter schedule.
  • Veterans Day, November 11. It's a 2026 Discover Pass free day for day-use parking at state-managed lands, Dash Point State Park included. The free day doesn't cover overnight stays or rented facilities.
  • Dinner on the point. Gino's at the Point at 6912 Soundview Dr NE serves Italian food with Pacific Northwest ingredients and Peruvian touches. According to NE Tacoma Buzz's neighborhood restaurant guide, it occupies the building that housed the Lobster Shop from 1977 to 2014, which Gino Rivera and Kelly bought in 2017.

The Center at Norpoint, where both pier design meetings took place, has a full late-fall schedule. Parks Tacoma's Norpoint Turkey Trot starts at 9 a.m. on Thanksgiving, November 26, with a 3K and a chip-timed 5K through Northeast Tacoma. The NE Tacoma Healthy Kids Coalition runs a food drive at the center from November 2 through December 18. The 50+ Thanksgiving Potluck is at noon on November 18. The free family Holiday Blast runs December 5 from 2 to 5 p.m.

To follow the pier itself, check the Parks Tacoma project page. The project contact listed there is Kristi Evans at (253) 305-1054. When that page posts a new update, look for news on the permit list. That will be the first real sign of when the fence can come down.

If you own a home along Dash Point's shoreline and want to know how the pier project and the beach around it fit into your property's value, Lori DeVore & Co. follows Dash Point waterfront changes closely and can walk you through it. Request a complimentary home valuation, and we'll start with your stretch of the shore.

Work With Lori

A passionate advocate for her community, she has served on numerous boards and committees and has chaired many successful gala fundraiser events, further demonstrating her commitment to both professional excellence and community involvement.

Follow Me on Instagram